SPR ENGINEERING REPORT – 08/27/2007
Baldy Mt. Electronics Site Summer of 2007 Work Season Progress Report
GENERAL SITE TASKS
Done: Surveying Northeast corner of the Jove Lode was found to be in a favorable location vis a vis the possible relocation of the New Head-end. Main Shack door replacement The new door swings inward and seals very well.
To be done: Seal openings under Main Shack.
Deferred: Old Structures removal Paint Ham Shack
AC POWER SUPPLY
Done: 206 SCR 532 Electrical Service Pedestal renovation Main Site Disconnect Switch repositioning 3/4" Electrical Service Conduit installation Main Shack Power Line Entry renovation New Head-end Electrical Service renovation
To be done:
Individual load measurement
Deferred: Power line fault analysis Burying of exposed electrical conduit
TOWER WORK
Done: Permanent Tower C installation Wispertel Repeater Units repositioning KTUN and KLDV receive antenna mount installation Temporary WISP Antenna Support Structure removal
To be done: “Apex” repeater antenna repositioning KTUN receive antenna repositioning KLDV receive antenna repositioning KUVO STL receive antenna repositioning
Deferred: Tower A West Guy-wire replacement
OLD HEAD-END WORK Temporary ground fault repair resolution Addressed by the installation of a dedicated 3/4" Electrical Service Conduit (see AC Power Supply group above).
To be done: Trans-ridge Conduit repositioning 220 volt to 120 volt Power Supply Auto Transformer reinstallation
Deferred: Trans-ridge Conduit renovation
NEW HEAD-END WORK
Done: KVOD & KUNC Receive Antenna Position Swap
To be done: Possible Repositioning of Support Structure
MONITORING & CONTROL SYSTEM
Deferred: System Assembly and Installation
UNINTERRUPTIBLE POWER SUPPLY
Done: Photovoltaic Panel Array Support Structure creation Concrete columns poured Battery Rack fabrication and delivery
To be done: Photovoltaic Panel Array Support Structure creation Treated 6’ x 6’ wood horizontal members installation
Deferred: Wind Turbine Generator Support Structure installation System Assembly and Installation
TV AND FM TRANSLATOR TASKS
Done: Translators Station-identifying label creation To be affixed. New KUNC translator installation
To be done: 88.3 KUNC Output Bandpass Filter Installation The filter is in place but is introducing a high SWR when it is connected. Note that the KUNC FM translator itself is interfering with the Channel 4/8 TV translator video signal (fine herringbone pattern). Channel 8, 10, and 12 TV translator relocation 107.9 KLDV Output Filter Installation 89.7 KUVO Output filter replacement
Deferred: 89.7 KUVO FCC power increase request Possible replacement of KLDV omni-directional transmit antenna 94.3 KBCO Output Filter Installation KUNC KU-band satellite downlink installation This may not be necessary.
Baldy Mt. Electronics Site
Conditional Use Permit
|